Based on the requirements of the Article 13, Chapter 4 of
the Procedures for Manufacture Licensing of Boiler and Pressure
Vessel, manufacture licensing survey for boiler manufacturer
shall include the following five aspects.
1. Verifying the resource of the boiler manufacturer including
production site, situation of staff, manufacturing and processing
equipment, inspection and testing facilities and instruments,
etc.
* The applicants for boiler manufacture licensing must
have independent legal status or have registered in local
governmental departments where the manufacturer is located.
* The applicant for boiler manufacture licensing should
have human resource suitable for manufacture and management
of boiler production. The requirements for technical personnel
will be different among various level boiler production. Please
refer to the Article 8 and the point 1 of Articles 11¡ª14
of the Requirements for Boiler and Pressure Vessel Manufacture
Licensing for details.
*?/font>The
detail requirements for workshop and technical facilities
of different levels of boiler manufacture licensing are listed
in the Article 9, points 2 and 3 of Article 11 and point 2
of Articles 12¡ª14 in the Requirements for Boiler and Pressure
Vessel Manufacture Licensing.
* The resources requirements for the manufacture licensing
of organic fluid heater and for level-A boiler parts may refer
to the Article 10 of the Requirements for Boiler and Pressure
Vessel Manufacture Licensing.
2. Review the quality manual and related documents. The quality
management system of the applicant should satisfy the requirements
of Chapter 4 (Articles 27¡ª43) of the Requirements for Boiler
and Pressure Vessel Manufacture Licensing.
3. Check the implementation of quality management system
4. Check the relevant technical document including the applicable
safety technical codes and standards, material for pressure-containing
components, structure of products, inspection and testing
of products, safety appliances and instruments, documents
on delivery and name plate of the products, etc.
5. Examine and test of the trial products. The trail product
must full comply with the relevant requirements of Articles
44¡ª50 of the Requirements for Boiler and Pressure Vessel
Manufacture Licensing.
According to the
stipulation of Article 15 in the Procedures for Manufacture
Licensing of Boiler and Pressure Vessel, the survey team should
complete a written survey report based on the survey results.
The conclusion in survey report shall be classified as ¡°accord
with the requirements¡±, ¡°need to rectify¡± and ¡°disaccord
with the requirements¡±. On the bases of the article 16 of
the same ¡°procedures¡±, the survey team shall notice the
manufacturer in writing if the survey conclusion is ¡°need
to rectify¡± or ¡°disaccord with the requirements¡±.
Based
on the stipulation of Article 23 of the same ¡°procedures¡±,
this outline is also applicable for license renewal of the
boiler manufacturer.